Scope Of Project:

Construction of Eight Lane Carriageway starting near junction with MDR-1 (Baonli-Jhalai road) to End of interchange on NH-116 near village mui (Ch. 247.310 – 292.950) section of Delhi – Vadodara Access Controlled Green field Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana in the State of Rajasthan.

Project Details:

Total Length: 45.64 kms

Carriageway:
Total 15m 15m = 30m
Paved Shoulder – 3m Either Side
Earthen Shoulder – 2m Either Side
Median – 22m including Shyness
TOTAL CARRIAGEWAY WIDTH – 62m

SLIP ROAD cum Toll Booth: 1250m

Service Road / Connecting Road:  (1400+3152)m

Toll Plaza:  1 No. @ Ch. 291+100

Rest Area:  2 No. @ Ch. 247+600 & 274+150

Project Milestone:

Project Milestone-1
  • 256th Day from Appointed Date (30th August, 2021)
  • Stage Payment Statement Certified up to 10% of Contract Price (i.e Rs. 125.81 Cr.)
Project Milestone – 2
  • 438th Day from Appointed Date (28th Feburary, 2022)
  • Stage Payment Statement Certified up to 35% of Contract Price (i.e Rs. 440.34 Cr.)
Project Milestone – 3
  • 620th Day from Appointed Date (29th August, 2022)
  • Stage Payment Statement Certified up to 70% of Contract Price (i.e Rs. 880.68 Cr.)
Project Milestone-4 & Scheduled Completion Date
  • 730th Day from Appointed Date (17 December, 2022)
  • Completion of Construction in Accordance with the Contract Agreement

Client/Authority:

National Highways Authority of India

EPC Contractor:

M/s HG Infra Engineering Ltd.

Project Length:

45.64 kms

Appointment Date:

18 December 2020

Schdeuled date of completion:

17 December 2022

Authority's Engineer:

M/s Dhruv Consultancy Services Ltd. In JV With M/s Chaitanya Projects Consultancy Pvt. Ltd.

Project Chainages:

  • Project Start Chainage – Ch. 247+310
  • Project End Chainage – Ch. 292+950

Date of LoA:

26 February 2020

EPC Agreement signing date:

22 July 2020

Construction Period:

730 days (2 Years)

Maintenance Period:

10 Years from the Date of Completion Certificate