Construction of Eight Lane Carriageway starting near junction with MDR-1 (Baonli-Jhalai road) to End of interchange on NH-116 near village mui (Ch. 247.310 – 292.950) section of Delhi – Vadodara Access Controlled Green field
Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana in the State of Rajasthan.
Project Details:
Total Length: 45.64 kms
Carriageway: Total 15m 15m = 30m Paved Shoulder – 3m Either Side Earthen Shoulder – 2m Either Side Median – 22m including Shyness TOTAL CARRIAGEWAY WIDTH – 62m
SLIP ROAD cum Toll Booth: 1250m
Service Road / Connecting Road: (1400+3152)m
Toll Plaza: 1 No. @ Ch. 291+100
Rest Area: 2 No. @ Ch. 247+600 & 274+150
Project Milestone:
Project Milestone-1
256th Day from Appointed Date (30th August, 2021)
Stage Payment Statement Certified up to 10% of Contract Price (i.e Rs. 125.81 Cr.)
Project Milestone – 2
438th Day from Appointed Date (28th Feburary, 2022)
Stage Payment Statement Certified up to 35% of Contract Price (i.e Rs. 440.34 Cr.)
Project Milestone – 3
620th Day from Appointed Date (29th August, 2022)
Stage Payment Statement Certified up to 70% of Contract Price (i.e Rs. 880.68 Cr.)
Project Milestone-4 & Scheduled Completion Date
730th Day from Appointed Date (17 December, 2022)
Completion of Construction in Accordance with the Contract Agreement
Client/Authority:
National Highways Authority of India
EPC Contractor:
M/s HG Infra Engineering Ltd.
Project Length:
45.64 kms
Appointment Date:
18 December 2020
Schdeuled date of completion:
17 December 2022
Authority's Engineer:
M/s Dhruv Consultancy Services Ltd. In JV With M/s Chaitanya Projects Consultancy Pvt. Ltd.